Confidential · Greenfield campus siting
Challenge
Four candidate parcels, a board deadline, and three conflicting views on which site could reach first energization. Two parcels sat behind a transmission corridor with no published queue position.
Approach
Tested each site against firm transmission capacity and connection queue position, opened direct utility engagement to confirm substation scope and staged capacity release, mapped fiber routes for carrier neutrality and physical diversity, and screened water allocation and permitting exposure against a phased campus layout.
Outcome
Two sites were withdrawn on transmission timing grounds. The recommended location carried written utility engagement, dual fiber entry on independent routes, and phase-two headroom on the same substation without a second connection application.